Key milestones and proposed dates for introduction of all SRDP delivery mechanisms:

Programme approved

23 Jan 08

Week 0

All implementation dates subject to January RDC recommending approval

Programme changes confirmed and assessed

By 31 Jan 08

1

LFASS - issue payments

End Jan/Feb 08

LEADER - announce LAGs & funding

By mid Feb 08

LEADER - 2nd call for LAGs, strategies & bids

By late Feb 08

Lay further SSIs

Mar 08

Including those for RDC - RP and RDC - LMOs

RDC - LMOs - issue guidance & forms

Mar 08

RDC - RP - Guidance published

12 Mar 08

7

FPMC - open to applications

By 12 Mar 08

7

Food Processing, Marketing & Co-operation; opening date subject to SSI approval.

Easter weekend

21-24 Mar 08

RDC - RP - initial IT systems ready

By 24 Mar 08

9

Necessary infrastructure, software, data & accounts all ready for staff & key stakeholders' familiarisation with Statement of Intent ( SoI) processing.

RDC - RP launch - announce Regional Priorities

25 Mar 08

9

FPMC - first round closes

31 Mar 08

10

SSIs approved

April 08

If negative (as currently envisaged) or later if affirmative process

RDC - RP - Open for applications ( SoI)

7 Apr 08

11

Allows for SSI approval and Easter break

RDC - RP - Respond to SoIs

From 30 Apr 08

14

Allows for minimum response time

CCAGS - Crofting Grant applications & payments

From Apr 08

Once SSI approved, existing forms & processes will continue with minimal change

Forestry Challenge Funds - open to applications

5 May 08

15

Woodland In and Around Towns (WIAT) and Forestry for People (F4P)

RDC - RP - IT system for Proposal available

By 12 May 08

16

To give staff and key stakeholders opportunity for familiarisation

FPMC - PAC meeting

w/c 12 May

16

Project Assessment Committee meet, with confirmation of awards thereafter

RDC - LMOs - closing date

15 May 08

16

Aligned with SAF

RDC - RP - Proposals system available

19 May 08

17

after SAF, and allows for staff familiarisation & estate days with system demos.

Skills Development - open for applications

From May 08

If SSI in force by April.

RDC - RP - first payments for Plan preparation

From Jun 08

19

RDC - RP - First RPAC meetings

From July 08

23

allows for submission & assessment of Proposals

RDC - RP - First contracts issued

From late Jul 08

26

LEADER - 2nd round approved

Jul/Aug 08

RDC - RP - first payments for Capital projects

From Aug 08

28

For 'actual cost' cases; 'standard cost' cases depend on Inspection schedules.

Forestry Challenge Funds - Assessment round

From 1 Sep 08

32

LEADER - funds to LAGs & project claims

From Apr 09

May also be smaller interim funding in 08-09 financial year

RDC - RP - first payments for Multi-annual land based

From Oct 09

Payment for these projects requires submission and processing of SAF 09


Note: all implementation dates are subject to formal approval of the Programme & domestic legislation as shown