NPF2 Action Programme – Action 55

Back to National Planning Framework 2 - Action Programme
Action

Deliver Craigmillar Regeneration.

NPF2 Paragraph Reference

87

Contribution to NPF Strategy

  • Supports the development of Scotland's cities as key drivers of the economy.
  • Promotes development which helps to improve health, regenerate communities and enable disadvantaged communities to access opportunities.
  • Promotes more sustainable patterns of travel, transport and land use.
  • Encourages a supply of homes that are affordable in places where people want to live.
Milestones

2009 onwards - Implementation of PARC Craigmillar development programme. Consider the need for environmental assessment, appropriate assessment and detailed scheme level mitigation at plan or project level.

Lead Partner(s)/Delivery Bodies

PARC Craigmillar URC
City of Edinburgh Council, Developers, EDI Group, community, Scottish Government (Housing and Regeneration Directorate).
Progress

achievements to date include completion of over 200 new homes in Wauchope & Greendykes masterplan areas; a 58-unit development for Link Housing Association is under construction; and negotiations are underway to develop a further 93-unit development in Wauchope Square. Craigmilla,PARC has commenced construction work at

Niddrie Mill & St Francis Joint Campus Primary Schools have been completed, as has Castlebrae all-weather football pitch. In the town centre the White House refurbishment and public realm improvement work has been completed. Investment has been secured from City of Edinburgh Council to build a £9.5M Neighbourhood Office and Community Library to start on site in Spring 2011; and further water and drainage improvement work has been secured to improve capacity for further developments in the town centre and Wauchope Square area

2009/10 - £2 million allocated from the Government's Town Centre Regeneration Fund for the renovation of the White House and town centre works.

February 2010 - shared equity scheme launched to support first time buyers

November 2009 - construction of additional phase of affordable homes underway

May 2009 - identified as SSCI exemplar project