CHAPTER FOUR CAPITAL COSTS OF THE BASELINE DWELLINGS

Overview

4.1 Detailed cost plans were prepared for each of the baseline dwellings, based on a Quantity Surveyor's take-off from the drawings and an analysis of the specifications of the baseline projects. For the flats, a cost plan was drawn up for a four storey block of eight flats comprising 2 x one bedroom flats, 3 x 2 bedroom flats and 3 x 3 bedroom flats. The elemental costs for each flat were then apportioned on a m 2 gross floor area basis.

4.2 Where necessary, adjustments have been made to the cost plans to reflect compliance with the Scottish Building Regulations, the Scottish Government's social housing technical standards and the Housing for Varying Needs requirements. The adjustments to account for the former included increased thermal insulation levels, and for the latter, included some increased floor areas and door widths.

Cost summary

4.3 The estimated capital costs for each baseline dwelling are summarised in table 4.1 below. Elemental summaries for each dwelling type are included in Appendix A.

Table 4.1: Capital cost summary for baseline dwellings

Gross Floor Area m 2

Capital Cost

£

Cost

£/m 2

2 bedroom house

73

£102,767

£1407

3 bedroom house

88

£114,279

£1298

1 bedroom bungalow

56

£101,276

£1808

2 bedroom bungalow

82

£121,108

£1476

1 bedroom flat

56

£74,876

£1337

2 bedroom flat

61

£80,519

£1320

3 bedroom flat

85

£107,609

£1266

4.4 These costs are broadly in line with the cost allowances within the former Communities Scotland grants application process.

Key assumptions

4.5 Key assumptions made in the development of the cost plans and agreed with the project's steering group are outlined in table 4.2 overleaf.

Table 4.2: Key assumptions in capital cost plans

Cost base date:

1st quarter 2008

Assumed location:

Central belt

Preliminaries:

17%

Contingency:

2.5%

Design fees:

8% (as advised by steering group)

Scale of housing scheme:

30 units

Land acquisition costs:

Excluded

Developer's management & administrative costs:

Excluded

Impact on density of development

Excluded

4.6 It should be noted that whilst the cost plans are based on schemes located in the central belt, the costs are equally applicable to developments in other locations within Scotland, subject to the application of the relevant Building Cost Information Service ( BCIS) or other published regional adjustment factors.