OPTION 31: INTRODUCTION OR RETENTION OF EXTENSIVE CROPPING (BIODIVERSITY CROPPING)
East
Income foregone: | Gross Margin | | | | |
| Spring Barley | £282.00 | per ha | | |
| Spring Oats | £260.00 | | | |
| Gross Margin average: | | | £271.00 | per ha |
| 100% yield reduction | | | £271.00 | |
| 15% yield reduction | | | £40.65 | |
Additional costs: | | | | | |
| Contractor's charge for ploughing field in spring-time when regular farm staff engaged in other peak-time activities | £42.00 | | | |
| 50% of Contractor's charge, assuming that farmers will plough at least 50% of their spring crop stubbles in the springtime using their own labour/farm staff. | | | £21.00 | per ha |
| Stone removal, assuming it will take 1 tractor/trailer driver and 2 gatherers one hour to clear each hectare @ | £6.80 | per hour per worker | £20.40 | |
Total additional costs: | | | | £41.40 | |
Costs saved: | Spraying costs | | | £21.50 | |
Total costs saved: | | | | £21.50 | per ha |
TOTAL NET COST 'EAST': | | | | £60.55 | per ha |
West
Income from established extensive crop: | Economic value of crop (turnip/kale) taken out of grass | | | | |
| Rental value of turnips: | £370.00 | | | |
| Rental value of kale: | £200.00 | | | |
| Average rental value of crop: | | | £285.00 | per ha |
Total income: | | | | £285.00 | |
Income foregone: | Rental value of grass: | £200.00 | | £200.00 | |
Additional costs: | Crop establishment costs (using contracted labour): | | | | |
| Ploughing | | | £42.00 | |
| Discing | | | £21.60 | |
| Rolling | | | £12.40 | |
| Sowing (with fertiliser) | | | £24.70 | |
| Seed cost (average) | | | £38.75 | |
| Stone removal, assuming it will take 1 tractor/trailer driver and 3 gatherers one hour to clear each hectare @ | £6.80 | per hour per worker | £27.20 | |
Total additional costs: | | | | £166.65 | |
TOTAL NET COST 'WEST': | | | | £81.65 | per ha |
Management payment is the average of the 'West' and 'East' figures:
Payment rate: | East' | £60.55 | | |
average of the 'West' and 'East' figures | West' | £81.65 | | |
| | | £71.10 | per ha |
Overall cost: | | | | |
| | | £71.10 | per ha |