RISK MANAGEMENT IN THE PROCUREMENT PROCESS
Introduction
This guidance outlines how to assess the risks presented during the procurement process. A risk assessment would typically be carried out for a high value/complex procurement exercise.
Risk can be defined as uncertainty of outcome (whether positive opportunity or negative threat). All projects contain risks that may affect their costs and quality, and the time taken to complete them. Risk management is a planned and systematic process consisting of:
· Identification: determine what the risks are;
· Assessment: determine the likelihood of the risks occurring and their potential impacts; and
· Monitoring and Response: identify options for dealing with risks or their impacts and monitor implementation of the preferred options.
Risk Identification
The initial identification of as many risks as possible is essential in terms of understanding the project. Potential major risks should be documented in the project risk register. Risks may be divided into 4 categories:
Strategic/corporate: Commercial, financial, political, environmental, strategic, cultural, acquisition, political and quality risks.
Programme: Procurement/acquisition, funding, organisational, projects, security, safety, quality and business continuity risks.
Project: Personal, technical, cost, schedule, resource, operational support, quality and provider failure.
Operations: Personal, technical, cost, schedule, resource, operational support, quality, provider failure, environmental and infrastructure failure.
Risk Assessment
The purpose of risk assessment is to assess the probability of risks occurring and their potential impact.
· Probability (or likelihood) is the evaluated chance of a particular outcome actually happening (including a consideration of the frequency with which the outcome may arise).
· Impact is the evaluated effect or result of a particular outcome actually happening (usually considered in terms of effect in cost, scheduling and quality).
Risk probability is usually categorised by developing a risk probability framework. An example of a typical risk probability framework is shown below:
Very Low (Extremely unlikely, or virtually impossible)
Low (Low but not impossible)
Medium (fairly likely to occur)
High (More likely to occur than not)
Very high (Almost certainly will occur)
Risk Monitoring
One of the most common approaches to monitoring responses to risks is the use of a 'project risk register'. The risk register is set up during the start of the project, ready to record all the identified risks and the results o f their analysis and evaluation, see AnnexA for a project risk register template. Information on the status of the risk is also included.
An example of a typical project risk register is shown below:
Risk ID No. | Description of Risk | Probability/Impact | Control | Action Required | Owner | Target Date | Next review date |
1 | Ineffective contract monitoring | H/H | Develop Key performance indicators (KPIs) to monitor contract | Liaise with An Other, and (prior to finalisation of ITT) secure their involvement in tendering process | An Other | N/a | 3/0 4 |
2 | Inability to identify all sub-contractors or sub-contracting requirements at outset leading to a lack of control of sub-contracted prices | H/H | Develop system to identify prices as and when known reserving right to accept / reject as appropriate | Managed by An Other / Customer with Reviews 6 monthly | An Other | 12/0 3 | 2/0 4 |
Key: VH = Very High H = High M = Medium L = Low VL = Very Low |
A project risk register may have an associated 'summary risk profile' which is a simple mechanism to increase visibility of risks by charting levels of impact and likelihood. It is a graphical representation of information normally found on the existing project risk register.
Ownership if risk must be clearly defined and documented within the project risk register and agreed with the individual owners, so that they understand their various roles, responsibilities and ultimate accountability. Individual owners should have the capability, authority and experience to deal with risk/s allocated to them.
Control
The risk assessment process requires that risks logged on the register are controlled. Responses to risk can be divided into four response categories:
Transfer: For some risks the best response may be to transfer them. This might be done by conventional insurance, or it might be done by paying a third party to take the risk in another way.
Tolerate : Ability to do anything about some risks may be limited, or the cost of taking any action may be disproportionate to the potential benefit gained. In these cases the response may be toleration.
Treat: By far the greater number of risks will belong to this category. The purpose of treatment is not necessarily to obviate the risk, but more likely to contain the risk to an acceptable level. The actions that an organisation takes in treating risk are called "internal control" - they are actions instigated from within the organisation (although their effects may be felt outside of the organisation) which are designed to contain risk to acceptable levels.
Terminate : Some risks will only be treatable, or containable to acceptable levels, by terminating the activity. It should be noted that the option of termination of activities may be severely limited in government when compared to the private sector; a number of activities are conducted in the government sector because the associated risks are so great that there is no other way in which the output or outcome, which is required for the public benefit, can be achieved.
Tools typically employed to control risk
Identified risk can be controlled within the procurement process and the tools typically employed by the buyer to enable this control are described below.
Bonds and guarantees
A bond is a legally enforceable financial guarantee given by a third party (the guarantor) to a purchaser (the client) to guarantee the obligations of a supplier of goods, works or services (the contractor) under a contract. The guarantor agrees to pay the client a sum of money if the contractor defaults on its obligations. The purpose of requiring a bond is to help the client meet the extra expenses to remedy the default and/or complete the contract. More information is available on bonds and guarantees at Annex B.
Escrow
'Escrow' is a legal term which means 'money, goods or a written document, held by a trusted independent third party (Escrow agent), pending the fulfilment of some condition'. Escrow agreements are applicable to all types of business critical material most commonly the source code for bespoke software, or inte llectual property. More information is available on escrow at Annex C.
Conditions of Contract
Conditions of contract ensure clear contract arrangements and will normally contain a number of clauses that will protect the organisation against a variety of risks, for example : property and risk; patents, information and copyright; indemnity and insurance; intellectual property, etc. More information is available on conditions of contract at Annex D.
Contingency Plans
A contingency plan may be produced that provides an outline of decisions and considers the programme's effects on public services and ensure that decisions are taken about those for which contingency arrangements will be needed. For example, take up of a new service is delayed and/or much less than expected, so the previous delivery options have to continue to run in parallel. Milestones relating to contingency measures should be defined in plans, and ongoing checks that the milestones are being achieved as expected.
A typical contingency plan is likely to contain:
· Plan description: brief description of the scope of the activity, planning assumptions, pre-requisites and constraints
· Information concerning the event/in cident that is the trigger for implementation of the contingency plan
· Activity Network or overall schedule information
· Information on key (outcomes and/or products) and/or Benefits (dis benefits) expected
· Budgetary information
· Table of resource requirements (to be assigned should the defined circumstances
occur).
Resource allocation may be dependent on contracts- in this case details of contracts should be included
· Risks and Issues
· Plan owner
· Details of distribution and storage (showing how people will get a copy of the plan so that they can take the appropriate action).
Risk Assessment Process
The following tables outline is a practical risk assessment guide to assist the Client and buyers through each stage of the procurement process, including links to further information and useful guidance.
1. At the Strategic assessment stage:
1.1 Have the major risks been identified?
· Potential major risks (including strategic, political and legislative risks) should be documented in the risk register.
The risks of success (e.g. take-up or usage greater than expected) will need to be considered.
1.2 How will risks be managed?
· Determine how risks will be allocated (to whom allocated and why) with high-level plans for managing them.
1.3 Have assurance measures for the programme been put in place?
· Ensure that stakeholders to the programme (e.g. internal audit, specialists and/or peer
reviewers co-opted onto the programme board) are appointed, to challenge
1.4 Is there a contingency plan? · Consider the programme's effects on public services and ensure that decisions are taken about those for which contingency arrangements will be needed.
· Milestones relating to contingency measures should be defined in plans, and ongoing checks that the milestones are being
2. At the Business justification stage:
2.1 Are there processes to identify, assess, allocate and monitor current, anticipated and emerging risks?
· There must be a risk management strategy, with named individuals who have responsibility for managing specific risks.
· For IT-enabled projects, the risk assessment should include information security risks; for e-government, risks relating to poor take-up should be considered.
· For construction projects, risks relating to health and safety should be included in the project brief.
2.2 Have the risks for each of the options been evaluated?
2.3 Have the risks for the preferred option been fully assessed?
· Assessment of costs, benefits and risks should be documented in the options appraisal section of the business case.
· There should be plans for managing and allocating the risks associated with the
2.4 Have the 'worst case' implications associated with these risks been assessed?
· Details should be set out in the Project Plan, Project Initiation Document or equivalent; for construction projects this information should be in the updated Project Execution Plan.
· Risks should be financially assessed and an allowance quantified for the risks.
2.5 Are the costs and time implications of managing the risks included in the cost and time estimate or treated as separately?
· Costs and time for managing risks should be identified as a separate risk allocation.
· For construction projects, residual risk will also have to be considered.
2.6 Has the project assessed whether it is breaking new ground in any areas?
· To make a meaningful comparison, carry out a high level assessment of similar projects in departments and or relevant private sector projects; seek expert advice if required, where innovation is identified as high risk.
2.7 Should the project be broken down into a series of small steps?
(Note: this is mandatory for IT enabled projects)
· Modular or incremental approaches to the project help to break it down into manageable components and reduce risk and, importantly, how to reassemble the
3. At the Procurement strategy stage:
3.1 Are the major risks identified, understood, financially evaluated and considered in determining the procurement strategy?
· There should be an overarching risk management strategy. Plans for risk management must include plans for managing the risks that cannot be transferred, such as business and reputational risk; useful guidance on Risk Allocation is available at http://www.ogc.gov.uk/documents/RiskAllocationModel.pdf
As at Business justification stage -
· For construction projects, health and safetyrisks for the whole life of the project should be identified, see Section 5 of Scottish Executive's Construction Works Procurement Guidance, www.scotland.gov.uk/spd.
· For IT-enabled projects, risks relating to IT
3.2 Are there risk management plans?
· There should be risk management plans that cover all of the risks, with responsibilities for managing each risk clearly identified and allocated; a risk reporting process in place for upward referral of risks and a contingency
3.3 Have all the issues raised in previous review(s) been satisfactorily resolved?
· The risk register should be regularly reviewed by the project team and a record kept of appropriate action taken.
3.4 Are the external issues being addressed? These include the statutory process, communications, public relations
· External risks must take account of the current business environment, the stakeholders, their expectations and
priorities, which should be managed through
4. At the Readiness for service stage:
Areas to probe Best practice
4.1 Have the risks and issues that arose in the contract award and implementation phase been
properly managed?
· The risk register should show that outstanding actions have been addressed. The remaining risks should only be those concerned with commissioning and operational service delivery; there should be
4.2 If there are unresolved issues, what are the risks of implementing rather than delaying?
· Updated Project Plans should include an assessment of all remaining issues and risks and a way forward supported by sensitivity analysis. If delay is inevitable, project manager must approve the revised plan for
4.3 Are there arrangements to minimise the risks to the business in the event of major problems during implementation and rollout?
· Business Continuity Plans and Contingency Plans should be in place in the event of late delivery and/or failu re by end-users to take up new services; these should be tested and agreed with stakeholders and suppliers.
· For IT-enabled projects, there should be evidence of information assurance including risk assessment and management.
4.4 Does the contract reflect standard terms and conditions and (where applicable) the required level of risk transfer?
· Standard forms of contract should be used; if not, the reasons for a different approach should be justified. Any changes to standard terms and conditions will need to be assessed for their impact, legality and acceptability. Plans for risk transfer should be analysed against the risk management strategy. Appropriate conditions of contract
4.5 For longer term partnering contracts, have the re-competition issues been considered?
· Re-competition issues should be addressed before letting this contract and appropriate 'handover' clauses included in the contract.
ANNEX A - PROJECT RISK REGISTER TEMPLATE
Risk Register for «Project Title»
Reference «Project reference»
Risk ID No. | Description of Risk | Probability/Impact | Control | Action Required | Owner | Target Date | Next review date |
1 | Ineffective contract monitoring | H/H | Develop Key performance indicators (KPIs) to monitor contract | Liaise with An Other, and (prior to finalisation of ITT secure their involvement in tendering process | An Other | N/a | 3/04 |
|
| | | | | | |
Key: VH = Very High H = High M = Medium L = Low VL = Very Low |
ANNEX B - BONDS AND GUARANTEES
References to "the EU rules" are to the EEC Treaty, the EU procurement directives as implemented in UK legislation, rulings of the European Court of Justice and other relevant EU law.
1. INTRODUCTION
A bond is a legally enforceable financial guarantee given by a third party (the guarantor) to a purchaser (the client) to guarantee the obligations of a supplier of goods, works or services (the contractor) under a contract. The guarantor agrees to pay the client a sum of money if the contractor defaults on its obligations. The purpose of requiring a bond is to help the client meet the extra expenses to remedy the default and/or complete the contract.
2. SCOPE
This guidance covers some of the practical considerations when using bonds, the issue of calling 'on demand', and deals with five types of bond or guarantee:
-unconditional on-demand bonds;
-performance bonds;
-parent company guarantees;
-advance payment bonds; and
-retention bonds.
Buyers are strongly advised to seek appropriate professional and legal advice
on the use, choice, and drafting of bonds for a particular contract.
3. PRACTICAL CONSIDERATIONS
3.1 Bonds are generally provided by the financial market, either by a bank or a surety
company. The contractor and the guarantor will seek to establish the terms and
conditions under which the bond can be called. Buyers, for their part should want to
know that the guarantor issuing the bond is a sound, reliable and responsible corporate
body and be satisfied that if there is need to call the bond for payment the guarantor will
comply promptly.
3.2 There are at present no standard forms of bond for use in government. The wording
of commercial bonds can vary depending on which organisation is providing the bond,
who is involved in drawing it up and what the bond is expected to deliver. There is often
intense negotiation over the precise wording of bonds and legal advisers should always
be involved.
3.3 Generally, the additional cost of a bond is relatively small in comparison with the
price of the contract. This will depend to some extent on the terms and conditions the
client requires (whether the bond is on-default, or more onerous, on-demand) and the
degree of risk the guarantor attaches to the ability of the contractor to give a counter
indemnity and to repay any sum that is called.
3.4 The size of the bond is very important, because this impacts on the contractor's
bonding capacity. To require a large value bond has the same effect as an equivalent
number of smaller bonds. Generally, contractors will be unwilling to use up their b onding
line on large bonds for smaller projects and this can restrict competition.
3.5 In most cases, on-demand bonds are provided by banks who may regard them as
open credit notes and may require provisions to be made from borrowing facilities
against contingent liabilities. This can affect the contractor's financial resources and its
ability to compete for and undertake other work. A requirement for an on-demand bond
may therefore deter firms who would otherwise have tendered for the contract and/or
inhibit their ability to tender in the future.
3.6 In raising a bond or a line of bonding credit from a bank or a surety company, the
contractor may undergo independent professional financial vetting, Whilst the extent of
the cover which the market is willing to provide may give some indication of the
contractor's financial standing and prospects, the procedures applied vary greatly and
will not always involve a detailed check of performance or record.
3.7 A guiding principle of procurement best practice is that normally a contract should
not be placed with a contractor if there are reasonable doubts about the contractor's
ability to meet the terms and conditions of the contract satisfactorily. Such doubts may
arise in relation to the adequacy of the contractor's management and technical resources
to deliver on time and to the required quality standard, or where information available
suggests the contractor may have inadequate financial resources with consequent risk to
Exchequer funds
Bonds are not always necessary and are no substitute for considered
judgements about the risks of a particular contract and the capabilities and
financial resources of the available contractors. A decision to require a bond
must be part of an overall approach to risk management and should take
account of available measures to reduce the risk of default, including a proper
prequalification of tenderers. Buyers will need to exercise careful judgement in
assessing the costs and benefits of using bonds, many of which may not be
easily quantifiable.
4. UNCONDITIONAL ON-DEMAND BONDS
4.1 The terms and conditions of a bond determine the circumstances and mechanism by
which the bond can be called. An unconditional on-demand bond allows the client to call
the bond at any time. Unconditional on-demand bonds are only provided by banks and
are in effect certified cheques.
4.2 Because they are not linked to the performance of the contractor, unconditional ondemand
bonds can be called by the client at any time and without having to show any
cause or justification. The findings of the courts have been consistent that there is no
implied requirement for the calling to be fair or reasonable. Unconditional on-demand
bonds can, therefore, be used unfairly, usually as a threat to persuade the contractor to
do something it would not otherwise do, or which it is not contracted to do.
Unconditional on-demand bonds are essentially unfair and Ministers have said
that they should not be used in government procurement.
5. PERFORMANCE BONDS
5.1 A performance bond is usually provided at contract award, for an agreed percentage
of the total contract value (normally 10 per cent). Normally, the value does not reduce,
but performance bonds should have an expiry date (not necessarily a calendar date - it
can be linked to an event so that time slippage is automatically taken into account). If
the value of the contract increases, or the duration of the contract extends, then the
bond may need to be amended accordingly.
A performance bond will not of itself ensure that contracts are carried out
efficiently and to time, but it will be one of a number of commercial pressures
on the contractor to perform well. A performance bond can provide some
compensation if the contractor defaults on its obligations.
5.2 There are two basic forms of performance bond: the "conditional on-default bond"
and the much more onerous "conditional on-demand bond".
Conditional on-default performance bonds
5.3 Usually these can be called only following a serious breach by the contractor of the
agreed terms and conditions of the contract (which will include becoming bankrupt and
would normally allow the client to terminate the contract).
5.4 Conditional on-default performance bonds are fairly common within UK industry and
are mainly provided by surety companies. They have been criticised because they are
often written in outdated and obscure language. This has meant that when calls have
been made, guarantors have sometimes looked to the wording of the bond for reasons
not to pay.
Properly expressed conditional on-default performance bonds provide a third
party guarantee that the contractor will not default from a contract it has freely
entered into. They should be required where there are identifiable risks of
default by the contractor, subject to value for money considerations. Buyers
should seek legal advice that the wording clearly expresses the true transaction
and not assume that "traditional" wording will be appropriate. They must be
prepared to pursue this with the guarantor.
Conditional on-demand performance bonds
5.5 These are bonds which although 'on-demand' should include within their terms and
conditions:
-a mechanism for calling (so that the bond may be called only if certain procedures
have been followed, requiring senior personnel within the client's organisation to approve
the calling):
-a requirement for the client to identify the reason for calling (which reason may be
questioned and contested); and
-a cooling off period (during which the contractor may remedy the default).
5.6 There is a place for the use of conditional on demand performance bonds where the
costs or other consequences of default by the contractor are very high and, provided it is
properly called, the guaranteed sum will be paid without risk of dispute. Such bonds
retain some features of an unconditional on-demand bond. They can be called at the sole
discretion of the client, but only if the agreed conditions for calling are met. This should
prevent the client from acting in an arbitrary or unreasonable way and protect the
contractor from the bond being called without the due and proper consideration of
responsible people in the client's organisation. A cooling off period should allow the
contractor time to investigate and remedy a default.
Buyers should be aware of the burden that on-demand bonds can place on a
contractor. Conditional on-demand performance bonds should be used
sparingly on high risk and/or high value projects where the costs and/or other
consequences of default by the contractor are high and only after careful
consideration, including appropriate professional and legal advice.
6. PARENT COMPANY GUARANTEES
6.1 This form of guarantee is given by a parent company (or holding company) to
guarantee the proper performance of a contract by one of its subsidiaries (the
contractor), and can only be given where the contractor is owned by a parent company
or is the subsidiary of a larger group. Such a guarantee is free of cost to the client, but
may give less certainty of redress than a bond because it is not supplied by an
independent third party. However, whilst accepting less independence, parent company
guarantees for the proper performance of the contract can be more advantageous than
bonds. Rather than receiving a fixed amount in compensation, the parent company is
obliged to complete the contract (see paragraph 6.3). Costs for completion are borne by
the parent company - and these costs may be significantly more than the compensation
provided for in a bond. In addition, further recompense can be sought for time delays in
completion through the normal clauses incorporated in the contract.
6.2 The conditions of a parent company guarantee will usually give the parent company
the opportunity to remedy any default within a period of notice before the guarantee is
called. The liability can take several forms including a financial guarantee of completion
of the project itself or the employment of another contractor to complete the project.
6.3 Where problems arise under the contract, this fo rm of guarantee should discourage
the parent company from putting the contractor into liquidation solely to avoid losses in
completing the project or in paying damages for late or non-completion. Provided that
the parent company is financially sound and the guarantee is properly worded, the
performance and the completion of the contract can be safeguarded, but the way in
which the project is completed if the contractor defaults can to some extent, be at the
discretion of the parent company.
6.4 Because th e financial strength of the parent company may be linked to that of the
contractor, a parent company guarantee will be acceptable only if the parent company
(or holding company) is financially strong and its financial resources are largely
independent of those of the contractor, and is permitted in its memorandum of
association to provide guarantees. Checks should be made to ensure that the parent
being offered is not another subsidiary of the same group. It is also preferable if the
overall parent of the group signs the guarantee.
Buyers should be aware when vetting the contractor that a parent company
guarantee is only as good as the parent company (or holding company) itself. If
the financial position of the holding company is inadequate, then the guarantee
should be given by the ultimate parent company, if this is justified by its own
financial standing.
7. ADVANCE PAYMENT BONDS
7.1 This term is used to describe payments made to contractors before the customer has
received the equivalent value in return. An advance payment provides a contractor with
working capital, to enable commitments under the terms of the contract to be fulfilled;
advance payments are usually sought in return for a price discount.
7.2 Futher information about advance payments is available from the Scottish Public
Finance Manual.
8. RETENTION BONDS
8.1 These bonds are still rare in the UK but their use is likely to increase. They are
provided so that contractors (and their subcontractors) may be paid without the client
deducting retention money. As work is completed, the contractor is paid fully under the
terms of the contract. Normal practice is to provide conditional retention bonds issued by
a surety company that increase in value as payments are made in accordance with the
contract. The client is protected against default at the end of the defects liability or
guaranteed maintenance period up to the amount of the bond.
8.2 The traditional retention system is to withhold a percentage from payments made
during the course of the contract to accumulate a fund that is available to the client if
the contractor fails to rectify defects in accordance with the contract (usually 5.0 per
cent of the value of the contractor's work up to certified completion, reducing to 2.5 per
cent up to final acceptance). Usually, the first half (in legal terms a "moiety") of retained
money is paid to the contractor on certified completion and the second on final
acceptance that the contractor has fulfilled its contracted obligations. The cost of that
anticipated loss of cash flow is reflected in a contractor's tender pricing. Retention bonds
give contractors better and more certain cash flow through full payment at all stages
(without the deduction of retention money).
8.3 The use of retention bonds tra nsfers financing cost from the contractor to the client
(who is required to pay in full earlier) and will pass cash flow benefits to the contractor.
Their use will only result in a lower cost to the client if contractor are prepared to reduce
their tender prices accordingly. The option to offer a retention bond should be included in
the tender documents at enquiry stage.
The conditions of a retention bond should relieve the client from failure by the
contractor to rectify defects in accordance with the contract up to the value of
the bond. Buyers will need to consider the balance of costs and benefits in
deciding whether to require and/or accept retention bonds. When used they
should be conditional on-demand, issued by a surety company. Buyers should
take legal advice that the wording expresses the true intention of the
transaction.
9. USING BONDS IN BUILDING AND CIVIL ENGINEERING CONTRACTS
This guidance deals with the use of bonds and guarantees for all types of procurement.
Further guidance on using bonds in construction works projects is available in the
Scottish Executive's Construction Works Procurement Guidance available on the SPD
website at www.scotland.gov.uk/spd
ANNEX C - ESCROW AGREEMENTS
'Escrow' is a legal term which means 'money, goods or a written document, held by a
trusted independent third party (Escrow agent), pending the fulfilment of some
condition'.
Escrow is a tripartite agreement made between the supplier, the buyer a nd Escrow agent
governing release of material. This ensures that if a key supplier's business should fail,
or they are unable to maintain their contractual obligations, the material can be
accessed and released both safely and quickly - assuring continuity of business.
Escrow agreements are applicable to all types of business critical material most
commonly the source code for bespoke software, o r intellectual property.
In a typical Software Escrow Agreement the supplier of the software provides a copy of
the database content, website, instructions/ support manuals, other Intellectual
Property, source code to an escrow agent.
The agreement sets outs certain events under which the above can be released to a
licensed user of the software (the buyer). For example if the supplier goes into
bankruptcy or liquidation, a merger or acquisition takes place, or fails to properly
maintain the software or perform under the Licence Agreement.
Due to the technological advancements in the IT industry more and more organisations
are reliant upon third parties to supply bespoke software for their needs and to provide a
maintenance service for the same. Such an agreement is therefore essential in order to
protect the buyer from such a risk.
ANNEX D - CONDITIONS OF CONTRACT
The Scottish Executive like many organisations has standard terms and conditions of
contract which are available from the SPD website - www.scotland.gov.uk/spd
Purchase of goods - reference SETC1
Purchase of Services - reference SETC2
Purchase of Consultancy Services - reference SETC3
The Supply of goods - reference SETC4
The Sale of Goods - reference SETC5
Careful consideration must be given to what terms and conditions of contract should be
applicable to the contract. While the Scottish Executive Standard Conditions of Contract
should be used, consideration should also be given as to whether these are wholly
appropriate for the circumstances of the contract in question, and if in doubt advice
should be sought from Scottish Executive Solicitors. Examples of clauses, relevant to
risk are outlined below but should only be viewed as such - legal advice on clauses most
appropriate to the specific project should be sought in all cases.
Intellectual Property Rights (IPR)
Scottish Executive standard terms and conditions (SETC's) include a condition covering
IPR. It is very important to include such a condition in all contracts where intellectual
property is involved and there is any possibility of the contra ctor producing or having
access to, any material, which is subject to copyright.
Alternative provisions will be required if it is intended that intellectual property rights are
to remain with the contractor. If this is the case the contractor should issue a licence
permitting the client to use those rights. For example:-
" The Contractor hereby grants to the Client a non-exclusive licence to use,
reproduce, modify, adapt and enhance the material which is generated in the
performance of the Contract. Such licence shall be perpetual and irrevocable."
SETC's also include a condition containing an indemnity where there is any possibility of
the contractor using any third party intellectual property without permission, to protect
the Executive against any claim for infringement of that third party's intellectual property
rights.
The conditions set out will need to be expanded upon in certain types of contract which
involve complex IPR arrangements; guidance should always be sought from Scottish
Executive Solicitors in such circumstances.
Extract from: Scottish Executive standard terms and conditions of contract
1. PATENTS, INFORMATION AND COPYRIGHT
1.1 It shall be a condition of the contract, except to the extent that the Goods or
Services incorporate designs furnished by the Purchaser, that nothing done by the
Supplier in the provision of the Goods or Performance of the Services shall infringe any
patent, trade mark, registered design, copyright or other right in the nature of
intellectual property of any third party and the Supplier shall indemnify the Purchaser
and the Crown against all actions, claims, demands, costs and expenses which the
Purchaser or the Crown may suffer or incur as a result of or in connection with any
breach of this Condition.
1.2 All rights (including ownership and copyright) in any reports, documents,
specifications, instructions, plans, drawings, patents, models or designs whether in
writing or on magnetic or other media:
(a) furnished to or made available to the Supplier by the Purchaser shall remain
vested in the Crown absolutely.
(b) prepared by or for the Supplier for use, or intended use, in relation to the
performance of this Contract are hereby assigned to and shall vest in the Crown
absolutely, and (without prejudice to Condition 20.2) the Supplier shall not and shall
procure that his servants and agents shall not (except to the extent necessary for the
implementation of this Contract) without the prior written consent of the Purchaser use
or disclose any such reports, documents, specifications, instructions, plans, drawings,
patents, models, designs or other material as aforesaid or any other information
(whether or not relevant to this Contract) which the Supplier may obtain pursuant to or
by reason of this Contract, except information which is in the public domain otherwise
than by reason of a breach of this provision, and in particular (but without prejudice to
the generality of the foregoing) the Supplier shall not refer to the Purchaser or the
contract in any advertisement without the Purchaser's prior written consent.
1.3 The provisions of this Condition shall apply during the continuance of this Contract
and after its termination howsoever arising.
Extract from Scottish Executive bespoke conditions of contract for an IT
services contract
1. OWNERSHIP OF RIGHTS IN THE DELIVERABLES AND SOFTWARE LICENCES
1.1 Title to and risk in any tangible property embodying all Deliverables and
Specially Written Software shall vest in the AUTHORITY upon acceptance
thereof.
1.2 All right, title and interest of whatever nature and all Intellectual Property
Rights (including but not limited to copyright and patent application rights)
to the Specially Written Software and associated technical documentation
shall vest in and belong to the AUTHORITY free from any interest of the
CONTRACTOR or any third party, upon acceptance thereof. The
CONTRACTOR by its signature of the Contract assigns to the AUTHORITY
with full title guarantee all Intellectual Property Rights (including without
limitation thereof future copyright) in the Specially Written Software. The
CONTRACTOR will do anything which the AUTHORITY may reasonably
require in order effectively to vest such rights in the AUTHORITY whether
before or after the termination of the Contract.
1.3 The CONTRACTOR shall supply the AUTHORITY with a copy of the Source
Code of any Specially Written Software upon acceptance of the relevant element
of the Specially Written Software.
1.4 As regards the Intellectual Property Rights in the Deliverables, other than
the Specially Written Software, the CONTRACTOR shall grant, or shall procure
that the owner(s) of the Intellectual Property rights in the said Deliverables
grants, to the AUTHORITY a non-exclusive, royalty-free licence to Use,
reproduce, modify, adapt and enhance the said Deliverables. Such licence
shall be perpetual and irrevocable. The AUTHORITY shall be entitled to engage
a third party to Use, reproduce, modify, adapt and enhance the said
Deliverables on behalf of the AUTHORITY, provided that such third party shall
have entered into a confidentiality undertaking.